Complete rebuild of Capilano Suspension Bridge.
Phase 1:
Rebuild west bridge anchor block, replace hardware connecting main bridge to support cables. Load test support cables using aquadam.
Phase 2: Replace main bridge cables and east end connecting hardware.
Phase 3: Replace deck support joists using work platforms suspended below bridge.
|